Convergence Acceleration of High Reynolds number Transonic Flow with Hyperbolic Navier-Stokes Equations
JAXA Supercomputer System Annual Report April 2016-March 2017
Report Number: R16E0064
- Responsible Representative: Yuichi Matsuo(Aeronautical Technology Directorate, Numerical Simulation Research Unit)
- Contact Information: Atsushi Hashimoto(hashimoto.atsushi@jaxa.jp)
- Members: Atsushi Hashimoto
- Subject Category: Basic Research(CFD)
Abstract
We evaluate the hyperbolic equations for one and two dimensional advection-diffusion equations.
Goal
We improve the convergence of high Reynolds number flow by using the hyperbolic equations proposed recently.
Objective
We evaluate the hyperbolic equations for one and two dimensional advection-diffusion equations.
References and Links
N/A
Use of the Supercomputer
We develop a code of hyperbolic equation and evaluate the method.
Necessity of the Supercomputer
We need a supercomputer for three dimensional flow analysis.
Achievements of the Year
Figure 1 shows a result of one dimensional boundary layer problem. We obtain an accurate result with the hyperbolic method. Figure 2 shows number of iteration for convergence. The number of iteration is small for the hyperbolic method and increases with first order slope. We found that the hyperbolic method is very efficient.
Publications
N/A
Computational Information
- Parallelization Methods: Serial
- Process Parallelization Methods: n/a
- Thread Parallelization Methods: n/a
- Number of Processes: 1
- Number of Threads per Process: 1
- Number of Nodes Used: 1
- Elapsed Time per Case (Hours): 0.1
- Number of Cases: 20
Resources Used
Total Amount of Virtual Cost(Yen): 6,439
Breakdown List by Resources
System Name | Amount of Core Time(core x hours) | Virtual Cost(Yen) |
---|---|---|
SORA-MA | 0.00 | 0 |
SORA-PP | 34.32 | 293 |
SORA-LM | 0.00 | 0 |
SORA-TPP | 0.00 | 0 |
File System Name | Storage assigned(GiB) | Virtual Cost(Yen) |
---|---|---|
/home | 0.58 | 5 |
/data | 542.53 | 5,117 |
/ltmp | 108.51 | 1,023 |
Archiving System Name | Storage used(TiB) | Virtual Cost(Yen) |
---|---|---|
J-SPACE | 0.00 | 0 |
Note: Virtual Cost=amount of cost, using the unit price list of JAXA Facility Utilization program(2016)
JAXA Supercomputer System Annual Report April 2016-March 2017